Things are continuing to move along on Second and Third Streets. Work is scheduled to begin soon on South Second and Third Streets. Below is a tentative schedule of work for the next few weeks. Please note the red text indicates work on South Second and Third Streets.
Week of July 20:
N. 3rd (Lincoln Hwy to Locust)
- Finish pouring concrete
N. 2nd (Lincoln Hwy to Locust)
- Pour concrete
- Begin manhole work between Lincoln and Palmer Court on Friday, July 24
* THIS WILL INVOLVE A ROAD CLOSURE
Week of July 27:
N. 3rd (Lincoln Hwy to Locust)
- Installation of tree’s
N. 2nd (Lincoln Hwy to Locust)
- Continue manhole work between Lincoln Hwy and Palmer thru Wednesday July 30
*THIS WILL INVOLVE A ROAD CLOSURE
- Continue pouring concrete
- Installation of remaining light bases
- Installation of tree’s
S. 2nd (Lincoln Hwy to RXR tracks)- Layout of construction plan
- Saw cutting
- Demolition of sidewalk
S. 3rd (Lincoln Hwy to RXR tracks)- Layout of construction
- Saw cutting
*NO demolition until 2nd St. is completed
Week of August 3:
N. 3rd (Lincoln Hwy to Locust)
- Could possibly see the start of precast curb and planter installation
N. 2nd (Lincoln Hwy to Locust)
- Final pouring of concrete
- Set light poles
- Could possibly see the start of precast curb and planter installation
S. 2nd (Lincoln Hwy to RXR tracks)
- Continued demolition and removal of sidewalk
*ALLEY ENTRANCE WILL BE CLOSED STARTING ON AUGUST 3 – 24 ON S.2ND (S. 3RD ALLEY ENTRANCE WILL REMAIN OPEN UNTIL WORK ON 2ND IS COMPLETED)
Week of August 10:
N. 2nd and 3rd (Lincoln to Locust)
- Installation of BRICKS!!!
S. 2nd (Lincoln Hwy to RXR tracks)- Begin to frame and pour the sidewalk and underlayment
Week of August 24:
N. 2nd and 3rd (Lincoln Hwy to Locust)
- Mill and resurface road!!!