Rise & Revitalize Downtown Construction Update May 27, 2009

West Lincoln Highway to Be Resurfaced

Project Area:

Lincoln Highway/IL Rt 38 from 4th Street to Stadium Drive

Project Scope:
Mill and resurface of the highway. At least 1 lane of traffic will remain open in each direction throughout the project.


*Estimated Timeline:

Completion date is likely to be late fall 2009.



2nd and 3rd Street Project UPDATE

April - Locust & Third (Water Main) COMPLETE


  • Closure on Locust from 3rd to 4th

  • Will last approximately 1 month

  • 3rd street will remain open
  • Vehicular access will be open to locations between 4th and the entrance to the Monat building on Locust Street.

May - 3rd Street by NB&T (Water Main) COMPLETE

  • Closure from Palmer to Locust
  • Could last approximately 1 month
  • Palmer Ct. will remain open and 3rd from Lincoln to Palmer will remain open
  • Reverse Palmer Ct. one-way to allow for traffic flow out of 3rd Street.
  • No blocking of Palmer will be allowed
  • NB&T Bank drive thru will remain open, but exit will be reconfigured

June-Corner of 3rd and E. Lincoln Hwy (Sanitary) COMPLETE

  • Limited pedestrian access on east side of street
  • Pedestrian access would be open on West side by the House and then when the East side is done the West side will close.
  • Closure from Lincoln Hwy to Palmer Ct.
  • Could last approximately 1 month

July/August NOW JUNE/JULY-Curb and gutter 3rd then 2nd UNDERWAY

  • Parking will be obstructed
  • Fencing and door ramps will be required
  • Possible spot closures at time for crosswalk work, etc.
  • Small storm sewer will need to be repaired at corner of 2nd and Locust St. that will involve a one lane closure at times.

September NOW AUGUST-2nd and 3rd sidewalk and landscaping

  • Parking will be obstructed at times
  • Fencing and door ramps will be required
  • Possible spot closures at times for crosswalk work, etc.

September/October-remaining sidewalk and landscaping throughout project area

  • Resurface of 2nd and 3rd Streets

Outdoor Cafes

Project Scope:

Three outdoor cafes have been added to the 2nd and 3rd streetscape project. The construction of the cafes will take place during the sidewalk improvements portion of the project. The cafes will be enclosed areas adjacent to the businesses. Food and alcohol will be allowed to be served in these areas. Adjacent parking spaces will be removed to create each cafe.

Locations/Parking:

Please note at the patio locations some adjacent parking spaces will be removed. Some of those spaces include 15 minute spaces. The City of DeKalb will also be working to convert other 15 minute parking spaces in the immediate area to long term parking to help off-set parking loss.

  • Hillside (1 parking space removed)
  • Eduardo's on S. Second Street (4 parking spaces removed on 2nd St.)
  • O'Leary's on S. Third Street (3 parking spaces removed on 3rd St., with motorcycle spaces being created and 1 parallel space in lieu)

Total current parking on 2nd and 3rd = 76 spaces

Total loss of vehicular spaces for patios = 6

Gain of 3 motorcycle spaces = 3

Pedestrian Pass Thru

Bid in late June, award in July with completion by Thanksgiving 2009.

East Lincoln Highway

Project Area:

East Lincoln Highway from 4th to 11th Street

  • Kiwanis Park, 11th and East Lincoln -Gazebo/Welcome Feature
  • 10th Street at Lincoln Highway Monument
  • 6th Street streetscape
  • Pocket Park on East Lincoln by Munson's Insurance
  • Decorative street light poles on East Lincoln, 4th Street to 8th Street

Project Update:

  • Bump-out curbs COMPLETE
  • Electrical conduits underground and lighting bases COMPLETE
  • Much of landscape platings around islands COMPLETE
  • By June 30th all completion expected, with poles previously delivered required factor alteration and delay in setting until June
  • Brick work expected in June at park by Munson's and all bump-outs
  • Precast stone monuments at 10th Street and park by Munson's are delivered and will be set within two weeks.
  • Aluminum planter towers being manufactured for setting before the end of June

*Information is subject to change based on project needs. Property/business owners will be notified of all major changes to this schedule and will be notified of regular process through regular construction update meetings, email notifications and website updates at www.renewdekalb.com.