Spring has sprung and work is back in full force on Locust Street.

Here is what is planned for the next few days...weeks:

GENERAL CONTRACTOR

Alliance has poured all the concrete available until the poles are removed. They are currently relocating the VB Plaza sign. They will begin cleaning up the lot at Locust and First late this week or early next week. Work will include removing the gravel, installing dirt, grading and then seeding. Once poles are removed by ComEd, they will return to finish concrete work.


FRONTIER:
All Froniter wires and poles should be removed as of Wednesday of this week.


COMED
Com Ed has made the last tie late last week and all power is now on the underground system. They are to start on May 4th removing the wire on the north side of Locust Street. They will be removing hardware off poles 1 block per day from 1st to 4th. At times there will be a 1 lane closures with 2 flaggers so road will never be fully closed. At times there will be sidewalk obstructions as wire comes down. All hardware is anticipated to be removed by Friday.

LANDSCAPE
Landscaper will be in the week of May 16th after all plants and shrubs are dug in the nursery.

CROSSWALKs
William Charles started removing failed materials today at the 3rd Street intersection They will continue to remove the failed product throughout this week. Once temperatures reach 50 and rising for 8hr periods they will begining painting the crosswalks with Streetbond 150. This is a special paint used for painting on streets. This is the same treatment as used on Annie Glidden Road. No thermoplast will be reinstalled.

As always, please contact Re:New DeKalb with any questions at 815-748-7788 or email jennifer@renewdekalb.com