Here's what's happening on 2nd and 3rd

South Second St.

Things really got rolling this week on S. 2nd. Most of the demolition and removals are done.

Work schedule for Week of Aug 10:
Please note work will flip back and forth as needed between the east and west sides of the street.

- underground & electrical work
- dig curbs
- pour curbs & gutter (alley driveway will come first)

South Third St.
No work is scheduled for the week of Aug 10.

North Second & Third St.
All the lighting and all but 3 trees are in. We are getting closer to completion, but some unanticipated delays did occur with the fabrication of the precast/veneer planter and curb elements. The overall schedule is not affected. Brick work is anticipated to be nearly complete by Aug 20 just in time for the Cornstruction sidewalk sales! Some fencing and/or safety barriers will still be in place in required areas on N. 2nd and 3rd over Cornfest weekend to ensure pedestrian safety.

Work Schedule for Week of Aug 10 & 17:
- Final sidewalk work near Hillside is anticipated to take place.
- Aug 14 & 15 precast planters will be installed on 2nd & 3rd
- Aug 17 – 20 bricks installation starting on N. 2nd and then move over to N. 3rd
- Aug 17 & 18 final precast curbs installed on 3rd Street