Friday, August 28, 2009

Weekend Update...

A few updated notes before the weekend –

N. 2nd and N. 3rd Milling and Repaving
Milling of N. 2nd and N. 3rd was postponed to Monday, August 31. No parking will be posted on N. 2nd and N. 3rd between Locust and Lincoln Hwy Monday – Wednesday for certain.

Lighting Issues
We have had some lighting issues on 2nd, 3rd and Lincoln Hwy between 1st and 2nd .
All lights should be operationally on 2nd and 3rd as of tonight. If you notice a light out please call with the location of pole. Lincoln Hwy lighting should be fixed by the end of next week.

Bricks
Brick work will be final completed on Monday, August 31 on N. 2nd and N. 3rd. All fencing will be removed at that time.