N. 2nd and N. 3rd Streets -
N. 2nd and N. 3rd are complete with the exception of some landscaping and sign installation.
Below is the construction update for S. 2nd and S. 3rd from Lincoln Hwy to the RXR tracks.
S. 2nd Street -
Thursday 9/17 – pouring curb
Friday 9/18 – week of 9/21 - pour sidewalk throughout area, including outdoor cafĂ© at Eduardo’s
*Tentative weekly schedule going forward on S. 2nd St
Week of Sept 28 – install precast planters
Week of October 5 – landscaping & trees and possible mill and resurface of S. 2nd and S. 3rd
Week of October 19 – installation of bricks
*As noted this is a tentative schedule and is subject to changes.
S. 3rd Street –
Week of September 21 – demolition and removal of sidewalk and curb.
- S. 3rd Street will be closed from Lincoln Hwy to RXR tracks
- Alley will be closed at S. 3rd St. but is open for access at S. 2nd St.
IDOT RT 38 Resurface Work –
The mill and resurface of Rt 38 from Stadium Drive to 4th Street will continue thru the end of October. This is night work that will take place from 8 p.m. to 6 a.m.
Union Pacific RXR Track Repair at RT 38 and RT 23 –
UP has informed us of a need to repair the tracks at this crossing. This will require a closure of the track for up to 2 weeks. This is tentatively planned for October 5. More information will follow soon.