The next few weeks are going to be extremely busy on S. 2nd and S. 3rd as we prepare to get things wrapped up. In addition to the streetscape project, the downtown is also experiencing IDOT and UP improvement projects.
Here is what to expect the next few weeks:
2nd and 3rd Street Project:
The rest of this week through the early part of the week of October 5 we will be finishing pouring all concrete on S. 2nd and S. 3rd as well as finishing up the electrical work on S. 3rd.
Veneers/precast planter boxes will be installed the week of October 5.
Landscaping and tree installation to follow the planter boxes and should be complete by October 12. Landscaping includes all planters on North and South 2nd and 3rd, trees and the sod in front of the Monat Building.
Milling and resurfacing will start the week of October 12 and should be wrapped up by October 23.
Bricks should be expected to start around the week of October 17.
RXR CLOSURE AT RT 38/23:
Union Pacific will be conducting a track closure starting on October 5 thru October 12 to repair 350 ft. of track.
Lincoln Highway Resurface:
IDOT continues to work on the RT 38 resurfacing. They will take advantage of the RXR closure on October 5 and finish the downtown portion of the milling during this time. There may be some daytime work due to the need for warmers temperatures for asphalt.