Friday, June 11, 2010

Lights, Bricks and Tree's Oh My!!!

Another great weather week resulting in lots of progress!

Here is where we are at block by block for the next week:

S. 1st - 2nd on ELHWY-
Friday 6/11 - lights are being installed and will be lit by Monday.
Monday 6/14 - bricks will begin to be installed starting at the corner of S. 2nd.
Tuesday 6/15 - trees will be installed and bricks should get completed.

All that will remain in this block will be the installation of the precast planters and the remaining landscaping. We will also need to put the benches and garbage cans back in. But all and all, after Tuesday things will be just about done!!!

S. 2nd - 3rd on ELHWY -

Friday 6/11 - begin installing lights
Monday 6/14 - complete lights and pull wires
Wednesday 6/15 - possibly begin brick work


S. 3rd - 4th on ELHWY -

Friday 6/11 - installation of conduit and under drains
Monday 6/14 - more underground work
The rest of the week - dig and pour light bases and then early next week get ready to pour sidewalk and underlayment.