We are preparing to move into Block 4 (1st to 2nd on the north side of Lincoln Hwy) tomorrow, Thursday, June 24, 2010. Here is what to expect as we work to move the construction across the road:
***PARKING LIMITATIONS***
Parking will be limited on Lincoln Highway on Thursday and Friday of this week from
1st to 4th Street on both the north and south side of Lincoln Highway from 7a.m.to 4p.m. daily.
South side:
Parking and traffic lane on the south side will open up next week once work is complete in block 3. Due to traffic control safety needs the full lane is required to be closed from 1st to 4th. Parking IS ALLOWED in block 1 since all work is done in this area. Park will not be allowed in block 2 and 3 while they are finishing the installation of bricks and light poles.
North side:
Parking and traffic lane will be closed from 1st to 3rd daily from 7a.m. to 4p.m.
***BLOCK BY BLOCK*** Here is what work to expect:
Block 1 - 1st to 2nd on the south side of Lincoln Highway
Wednesday, June 23 light repairs and final electrical work. There will be a lane closure up the rest of the week going from 1st to 4th due to the work in block 2 and block 3. Parking is open in Block 1. Late next week 6/28 planter bed walls will be installed and final brick work may be installed. This is minor work.
Block 2 - 2nd to 3rd on the south side of Lincoln Highway
Thursday/Friday, June 24 & 25 install light poles. Please note their will be one temporary pole in the middel of the block. We are waiting for the rest of the lights to come in so we will be using temporary poles in various places. Just know the one odd pole is not permenant. Also, late next week 6/28 planter bed walls will be installed and final brick work may be installed. This is minor work.
Block 3 - 3rd to 4th on the south side of Lincoln Highway
Thursday, June 24 - pour remaining concrete at each corner.
Friday, June 25 - install tree's, landscape fill and pull wire and complete electrical underground work.
First part of the week of June 28 - install bricks.Please note there will be a small section west of Munson insurance to the Cash Store that will not be bricked for a short time as we wait for additional materials to arrive
Last part of the week of June 28 lighting. Please note that we will be installing temporary lighting in Block 3 until the final lighting arrives.
Also late next week planter bed walls will be installed and final brick work may be installed. This is minor work.
Block 4 - 1st to 2nd on the north sidew of Lincoln Highway
Thursday, June 24 - removal of sidewalk - fence goes up!!!
Friday, June 25 - installation of underdrains
Week of 6/28 - installation of conduit and utility.