More progress on Lincoln and Locust. Here is an update of where things stand as of Friday, September 3, 2010:
Lincoln Highway
The final lighting elements arrived for the lighting fixtures on Lincoln Highway and are currently being installed. Most of the lighting should be compelted by the middle of next week. Lights are installed in the pedestrian pass thru. Street furnishings and landscaping is still to come, but will be done by the end of September.
Locust Street
1st to 2nd
Conduit is on on south side and road/sidewalk has been removed. Grading work will begin next week.
2nd to 3rd.
Conduit work has begun. Road removal is not completed yet. A large utility cabinet needs to be installed between the entrance to the Van Buer Plaza and the drive for NB&T. This will require brick removal and disruption of a landscape bed, but all materials will be replaced upon completion of the work.
3rd to 4th
Road removal is nearly done. Tuesday Sept 7 the contractors will remove the remaining road and sidewalk from PNC Bank drive thru to 4th St. Bank drive will be removed one half at a time to alow for access at all times. Utility work will follow on Wed.