Things got even messier this week, but we have made great progress as well. A couple of entrances along E. Locust were blocked for a few hours here and there. Appologies for the lack of advance notification. Hopefully the communication gliche has been fixed. As we have noted in the past, there will be spot closures from time to time to allow for the removal of road and sidewalk and longer closures once the concrete has been poured to allow for drying. Those closures should be coordinated with business owners. Random spot closures may occur from time to time to allow equipment to be moved and so on.
Please note starting on Saturday, September 18 the construction work will take place 6-days a week including Saturdays.
Here is a look at where things stand into next week:
Locust Street:
1st to 2nd - sidewalk/road removal is complete in this area. Stone will be put in and other grading work. Next week they will be framing and pouring curbs!
2nd - 3rd - Utility work is still underway in this block. Some excavation work got underway today, but more utility work to be done in this block.
3rd- 4th - removal of sidewalk and road is underway.
Lincoln Highway:
Lights should be complete this week. Landscaping will be coming on Monday, September 13, 2010. Benches should be next week as well. Last portion is the fence and handrail in the pass thru.
If you have questions please call Re:New DeKalb at 815-748-7788.