First, we forgot to mention that contractors are working on installing the thermoplast cross walks at the intersections of 2nd and 3rd on all 4 sides. This week they are grinding out the old cross walk paint. Next week they will begin stamping in the thermo plast. No road closures will be needed at 2nd, 3rd or on Lincoln. They will do half a section at a time on 2nd and 3rd. Then on Lincoln they will do the outer lanes and center lanes to keep traffic flowing.

Second, we were just informed that the contractors will be trenching across 3rd St tommorrow (Friday, Sept 10) in the morning. Traffic will be diverted from 3rd to Palmer. Work will be done by 11 a.m.